Work has begun on transforming our office spaces into one large unified room.
The walls in what was previously the Cookery Room, are being prepared and additional power sockets are being installed.
You can see the enlarged space for the welcome hatch. The radiator underneath will be moved to the opposite wall to allow a lower start to the window opening.
The security doors have been removed to make a larger entrance lobby. Our security system is going to be moved onto the next set of doors down (at the back of the photo).
In addition to the office space, we are getting new cabling into the school, including electricity and gas. This is the trench to house them, spanning the length of the Infant playground. The new cables are due to be laid and the trench is due to be filled in before the end of next week, ready for the new school term.