Construction Diary: week forty

As work continues on the main extension, the other re-modelling projects are nearing completion.

The school office is now functional, thank you to everyone for bearing with us during the transition phase.  To finish the job we await the replacement window to arrive for installation.

The trench in the Infant playground was successfully inspected by the Water Board on Friday.  We expect the tarmac to be relaid over the space early in the coming week.

The Well-being Hut is now constructed.  We will shortly be insulating the walls and adding flooring before heating and lighting can be added.